Carter 374 FV-700 Pile Driver for Sea Trestle

May 22, 2025
Latest company case about Carter 374 FV-700 Pile Driver for Sea Trestle

latest company case about Carter 374 FV-700 Pile Driver for Sea Trestle  0

Project Name: Bid Section 3 of the Dalu Line East Extension Waterway Improvement Project
Project Location: Tongyuan East Road, Pudong New Area, Shanghai
Model selection: Carter 374 VIBRA FV-700
Project Description:
In a landmark marine construction project for Pudong Airport's channel expansion, Caterpillar's next-generation CAT®374 excavator paired with VIBRA's FV-700quad-ecc entric pile hammer is setting new benchmarks in offshore piling performance.
Project Breakthroughs:
• Dual-Spec Piling: Successfully installed both 630mm (27m) and 816mm (22m) diameter piles in challenging marine conditions
• Extreme Power: 915KN excitation force delivers unmatched driving efficiency
• Daily Output: Consistently achieves 50-60 piles per day - doubling conventional productivity
• Marine-Adapted: Specialized stability features overcome wave action and tidal variations
Technical Superiority:
The FV-700's quad-eccentric technology combined with the CAT374's precision control creates the industry's most reliable marine piling solution, particularly for critical infrastructure projects requiring:
✓ Millimeter-perfect verticality
✓ Continuous operation in corrosive environments
✓ Adaptive performance across varying seabed conditions